Unit 6 Project Management

Unit 6 Project Management

Using the information provided in the Gantt chart below, construct the project activity network using the activity-on-node (AON) methodology, and label each node. Identify the critical path and other paths through the network.

Activity     Duration   Predecessors
A     3  
B     5   A          
C     7   A
D     3   B, C
E     5   B
F     4   D
G     2   C
H     5   E, F, G
 